For Dominion Energy customersBeta

Bill up? Let's break it down.

See what components are driving your bill up

Bill-reading check · Awaiting bills

Use downloaded PDFs or clear bill screenshots. Review screenshot text before analysis.

We know privacy matters. Nothing you add here is stored — PDFs are read in your browser and only their text is sent. If you'd rather not upload a PDF at all, choose Screenshots · private OCR: the image is read on your own device and only the reviewed text goes further.

Upload your bills

PDFs downloaded from your Dominion account. Upload at least two bills for the comparison period you want — monthly, quarterly, or yearly. Nothing is stored.

Bills added0 / 6

State watch

Know what's going on in your state

Only the latest and most consequential rate announcements, public hearings, and legislation affecting your residential electricity bill.

Sources reviewed October 25, 2026. A short, curated list of the latest major items — not a live or exhaustive feed. Open the official source for the latest dates and decisions.

Public hearingsPast hearing

Rider RGGI: public-witness hearing

October 28, 2026 · 10 a.m. Eastern · PUR-2026-00085

The SCC scheduled a hearing on Dominion’s request to reinstate its carbon-allowance cost rider. The October 21 public-witness registration deadline has passed; check the official schedule for changes and viewing details.

Bill impact: A proposed rider could add carbon-program costs to bills. A scheduled hearing is not approval of the charge.

Rate announcementsSCC decision

Transmission rider decision

2026 decision · PUR-2026-00056

The SCC’s Rider T1 fact sheet reports a projected monthly impact of 94¢ for a residential customer using 1,000 kWh, down from the originally proposed $2.90.

Bill impact: Transmission costs are a separate bill lever. This example is not a forecast for your household or your total bill.

Rate announcementsSCC review

Offshore wind rider annual update

Update filed October 31, 2025 · PUR-2025-00195 · rate year September 2026 – August 2027

Dominion's annual Rider OSW update covers the Coastal Virginia Offshore Wind rate year starting September 1, 2026. The filing reports the project cost forecast rising to $11.16 billion, including about $256 million of projected federal tariff costs, and asks the SCC to approve the updated expenditures.

Bill impact: Rider OSW is one of the largest single riders on Dominion bills. The rate-year amount is not set by this filing — a decision is pending on the SCC docket.

Rate announcementsApproved

Efficiency programs and Virtual Power Plant pilot approved

Final order August 3, 2026 · PUR-2025-00210 & PUR-2025-00211

The SCC approved Dominion's Phase XIV demand-side management programs, a three-year extension of its income- and age-qualifying efficiency programs, and a Virtual Power Plant pilot. Program costs are recovered through a separate rate adjustment clause.

Bill impact: Efficiency programs are paid for through rider charges on bills, and costs are reviewed each year, so the rider can change.

Rate announcementsSCC review

Line-extension policy review for large-load costs

Docket opened August 25, 2026 · follow-on to the Rider T1 decision

Following its Rider T1 decision, the SCC opened a docket for Dominion's proposed amendments to its line-extension policy. The changes are designed so that large-load customers fund the 'direct-connect' transmission facilities needed to serve them, applying prospectively.

Bill impact: This aims to keep growth-driven transmission costs off residential bills. The policy changes are proposed, not yet decided.

Bills & lawsEnacted

New law reviews utility costs and incentives

2026 Acts · Chapter 702 · Report due July 1, 2027

Chapter 702 directs the SCC to evaluate utility performance, consolidating riders, fuel-cost risk sharing, and cost-control incentives, with public input and legislative recommendations. The law itself does not set a new residential rate.

Rate announcementsApproved · in effect

2026–2027 fuel factor approved, with securitization

Order September 29, 2026 · PUR-2026-00058 · fuel factor in effect since July 1, 2026

The SCC approved Dominion’s 2026–2027 fuel factor to recover about $2.69 billion in projected fuel costs, and allowed roughly $922 million of under-recovered fuel costs to be financed over seven years instead of charged at once.

Bill impact: For a typical residential customer this means about $7.97 more per month for fuel plus $2.26 for the financing — roughly $10.23 a month instead of the $21.79 a one-year recovery would have added. Financing spreads the cost but adds interest over time.

Rate announcementsApproved · in effect

Base-rate increase approved for 2026 and 2027

Order November 25, 2025 · PUR-2025-00058 · effective January 1, 2026

In Dominion’s biennial review, the SCC rejected the requested $822 million (2026) and $345 million (2027) base-rate increases and instead approved $565.7 million for 2026 and $209.9 million for 2027. The order also created a new GS-5 rate class for very large users such as data centers, effective January 1, 2027.

Bill impact: For a typical residential customer, the approved rates add about $11.24 per month in 2026 and another $2.36 per month in 2027 — roughly 24% and 51% less than Dominion requested.

Proposals and filed bills are not approved rate changes. A policy update alone does not establish why your bill changed.